Optimised contractor involvement
Optimised contractor involvement (OCI) is a variation of the ‘early contractor involvement’ (ECI) model that has been adopted widely in the infrastructure sector on large and complex projects.
Devised by Steve Rowsell, Procurement Director for Crossrail, OCI is intended to ensure contract packages are subject to effective competition and maximum output with the available resources.
The subtle difference between ECI and OCI is that in ECI, a contractor’s skills are introduced early into a project to bring design buildability and cost efficiencies to the pre-construction phase. In OCI, contractors are brought in at a stage that is late enough for the target price to be quite firm, but early enough for them to be able to influence buildability and value engineering.
ECI has been used on by many public sector construction clients, however, some clients have been reluctant to adopt the strategy because of concerns associated with appointing contractors before permissions such as planning have been granted, and issues to do with attracting accurate and competitive prices from contractors when the design is not yet well advanced.
The OCI approach optimises contractor involvement, rather than simply trying to make it as early as possible, waiting till a point when the contractor is more likely to be able to offer an accurate and competitive price.
The contractor input into the design under OCI generally takes place post contract award, whereas in ECI, it takes place pre-contract award, under an arrangement such as a Pre-Construction Services Agreement.
The OCI approach may adopt a two stage selection process. The first stage is based on an assessment of the contractor’s technical and quality competence. The second stage involves the shortlisted tenderers carrying out a review of the client’s design. The tenderers then submit their final proposals, including a target price.
[edit] Find out more
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Reasons for using MVHR systems
6 reasons for a whole-house approach to ventilation.
Supplementary Planning Documents, a reminder
As used by the City of London to introduce a Retrofit first policy.
The what, how, why and when of deposit return schemes
Circular economy steps for plastic bottles and cans in England and Northern Ireland draws.
Join forces and share Building Safety knowledge in 2025
Why and how to contribute to the Building Safety Wiki.
Reporting on Payment Practices and Performance Regs
Approved amendment coming into effect 1 March 2025.
A new CIOB TIS on discharging CDM 2015 duties
Practical steps that can be undertaken in the Management of Contractors to discharge the relevant CDM 2015 duties.
Planning for homes by transport hubs
Next steps for infrastructure following the updated NPPF.
Access, history and Ty unnos.
The world’s first publicly funded civic park.
Exploring permitted development rights for change of use
Discussing lesser known classes M, N, P, PA and L.
CIOB Art of Building 2024 judges choice winner
Once Upon a Pass by Liam Man.
CIOB Art of Building 2024 public choice winner
Fresco School by Roman Robroek.
HE expands finance alliance to boost SME house building
Project follows on from Habiko public-private place making pension partnership for affordable housing delivery.
Licensing construction; looking back to look forward
Voluntary to required contractors (licensing) schemes.
A contractor discusses the Building Safety Act
A brief to the point look at changes that have occurred.
How orchards can influence planning and development.